Confusion over end date for Wembley High Road sewer works

$
0
0

 Street signs say that the sewer works in Wembley High Road will continue until January 31st 2018 but this is what Brent Council posted on its website yesterday with a completion date of January 5th LINK:
The sewer works on High Road, Wembley, are progressing well and the proposed end date for these works is now 5 January 2018.

To date Thames Water have:
  • Removed the traffic island
  • Excavated a shaft onto the sewer over seven meters deep
  • Tunnelled four meters downstream, towards Park Lane, to a point where there is no concrete in the sewer
  • Tunnelled upstream, towards Wembley triangle, eight and a half meters to the lateral connection from the former Brent House site and have tunnelled over fourteen meters to a point where all concrete has been removed.
  • Sink another shaft on the sewer
  • Replaced the sewer
Next steps:
  • Backfill the tunnels
  • Backfill the shaft
  • Permanent reinstatement of carriageway.

     Note: From the top of the 83 bus today (Thursday) it did look as if the backfill works have been completed. I have asked Thames Water for clarification.